Report of Perfromance Pledge for Year 2002
I. Introduction
As at December 2001, the members of the Performance Pledge
Work Group is as follows:
Coordinator: |
Mr. Paul Pang, Head of Academic Affairs Bureau |
Members: |
*Mr. Jason Ho, Head of Academic Computing Service
Dr. Tham Yiu Kwok, Head of Computer Service Bureau
Ms. Helen Ieong, Library
Ms. Eduarda Vu, Head of Registry
Mr. Sitou Ieng Kit, Head of Student Affairs Bureau
Ms. Carrie Lei, Head of Central Services
Mr. Chan Seng Iong, Head of Real Estate and Security
Ms. Jenny Lou, Center for Continuing Studies and Special
Programmes
Ms. Candy Lei, Head of Procurement Office
Ms. Leona Kwan, Head of Personnel Office
Mrs. Susan Kwok, Head of Treasury
Ms. Grace Chau, Faculty of Business Administration
Ms. Cecilia Leong, Faculty of Education |
* the Secretary of the Work Group and also serves as the Acting
Coordinator in case of absence of Mr. Paul Pang
Note: At the end of 2002, Sport Complex's project was combined
into CSD's project and Sport Complex is no longer counted as
a separate department in the PP project.
- The focus of 2002:
- For those departments that had launched their PP projects
before 2002, they should continue to implement the
projects actively, particularly emphasing the evaluation
of performance
and user needs in order to raise the quality of services;
- Gradually implement PP to the administrative offices
of academic units.
- In January 2002, FBA extended their PP project to the services
to academic staff.
- In February 2002, FED formally launched their PP project.
- Invited SAFP to provide 2 training sessions, on 17/10/2002
and 18/10/2002 respectively:
- Introduction to PP;
- Details about how to implement the project, introduction
of the 2 documents "Basic Requirements" and "Action
Plans";
- Discussion about the 2 documents.
For those departments that had already launched their
PP projects, they participated in part b) and c); those
staff members of the departments who did not attend any
related training before also attended part a).
For the other departments (including PRO, FSH, FLL, FST
and CPU), representatives attended the parts a)-c).
Totally 98 staff members attended the training.
II. Summary of Progress
As at December 2001, the number of departments participating
Performance Pledge is 11, with items of services 69.
As at December 2002, the number of departments participating
Performance Pledge is 12, with items of services 89.
III. Implementation and Evaluation
- Most items of services can 100% comply with the standards.
For those not 100% complying with the standards, we are improving
actively.
- Continue to adopt the mechanism of evaluation:
- Internal evaluation: Unit heads and the staff regularly
review the implementation, and analyze the statistics
for individual items of services, and analyze the feedback
of users (including complaints, suggestions, and results
of user surveys).
- Performance Pledge Work Group holds 2 regular meetings
to review the progress of all departments.
- QMC evaluates the overall progress of departments.
- Departments that have just started their projects will
submit a report to SAFP for their comments. We invite
SAFP to evaluation meeting of overall progress 2 times
a year.
- During the evaluation meetings with SAFP on 30/4/2002
and 6/12/2002, SAFP gave us very good comments of the
implementation of the Performance Pledge project.
|